| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 24 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 20 Jan 2025 | 97000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 16 Jan 2025 | 96000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 10 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
| 08 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
| 04 Jan 2025 | 94500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
| 31 Dec 2024 | 94000 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
| 26 Dec 2024 | 93500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 | |
| 24 Dec 2024 | 93500 m pipe laid and 1000 HTC given | Koothuparamba Proj AE 2 |