| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jul 2025 | 111000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 01 Jul 2025 | 110000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 27 Jun 2025 | 109000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 23 Jun 2025 | 108000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 19 Jun 2025 | 108000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 16 Jun 2025 | 107000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 12 Jun 2025 | 106000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 09 Jun 2025 | 106000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 05 Jun 2025 | 105000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 | |
| 03 Jun 2025 | 104000 m pipe laid and 1150 HTC given | Koothuparamba Proj AE 2 |