| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 May 2023 | Waiting for tested pipe | Kollam WS Sn 2 - AE | |
| 11 May 2023 | LoA prepared and send to the contractor, Site inspection conducted | Kollam WS Sn 2 - AE | |
| 08 May 2023 | LoA prepared and send to the contractor | Kollam WS Sn 2 - AE | |
| 05 May 2023 | LoA prepared and send to the contractor | Kollam WS Sub Dn - AEE |