| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Sep 2026 | Work completed | Chavara AE | |
| 01 Sep 2026 | Pump erection ongoing | Chavara AE | |
| 29 Aug 2026 | Pump erection ongoing | Chavara AE | |
| 21 Aug 2026 | Developing completed. | Chavara AE | |
| 19 Aug 2026 | Erection of pipes completed | Chavara AE | |
| 10 Aug 2026 | Erection of pipes completed | Chavara AE | |
| 20 Jul 2026 | Tube well work starts | Chavara AE | |
| 17 Jul 2026 | Site handover and work not start yet | Chavara AE | |
| 13 Jul 2026 | Site handover and work not start yet | Chavara AE | |