Status Date Overall Project Status Project Officer Contact
03 Aug 2023 Package 1-80% of work completed. Package 2- Work order issued .Site clearing work progressing. Package 3 and 6-One offer received. Package 5-Even after repeated tenders no offer has been received Hence retendered. Package 4-Since revised FS obtained, Estimate submitted to CE for TS Alappuzha KIIFB - AE 4
25 May 2023 Package 1-73% of work completed. Package 2-One offer received. Awaiting tender approval for issuing work order. Package 3 and 6- Even after repeated tenders no offer has been received Hence retendered. Package 5-One offer received. PQ approval awaiting for price bid opening. Package 4-Since revised FS obtained, Estimate submitted to CE for TS Alappuzha KIIFB - AEE 1
11 Apr 2023 Package 1-73% of work completed. Package 2-Work retendered with a due date of 10-04-2023. One offer was received. Technical bid opening on 11-04-2023. Package 3, 5, and 6-Work retendered with a due date of 10-04-2023. But No offer was received. Hence retendered. Package 4-Estimate is ready. Awaiting approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which is under consideration of KIIFB. Alappuzha KIIFB - AEE 1
03 Apr 2023 Package 1-73% of work completed. Package 2-Work retendered with a due date of 10-04-2023. Package 3-Work retendered with a due date of 10-04-2023. Package 4-Estimate is ready. Awaiting approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which is under consideration of KIIFB. Package 5-Work retendered with a due date of 10-04-2023. Package 6-Work retendered with a due date of 10-04-2023. Alappuzha KIIFB - AEE 1
18 Mar 2023 Package 1-71% of work completed. Package 2-Work retendered with a due date of 07-03-2023. One offer was received from M/s Nobletech, Documents are to be submitted for prequalification. Package 3-Work retendered with a due date of 07-03-2023. Since no offer received extended up to 20-03-2023. Package 4-Estimate is ready. Awaiting approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which is under consideration of KIIFB. Package 5-Work retendered with a due date of 07-03-2023. Since no offer received extended up to 20-03-2023. Package 6-Work retendered with a due date of 07-03-2023. Since no offer received extended up to 20-03-2023. Alappuzha KIIFB - AEE 1
17 Mar 2023 Package 1-71% work completed. Package 2-Work retendered with due date on 07-03-2023. One offer received from M/s Nobletech, Documents to be submitted for prequalification. Package 3-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 4-Estimate is ready. Awaiting for approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which under consideration of KIIFB. Package 5-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 6-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Alappuzha KIIFB - AE 4
13 Mar 2023 Package 1-71% work completed. Package 2-Work retendered with due date on 07-03-2023. One offer received from M/s Nobletech, Documents to be submitted for prequalification. Package 3-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 4-Estimate is ready. Awaiting for approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which under consideration of KIIFB. Package 5-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 6-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Alappuzha KIIFB - AEE 1
10 Mar 2023 Package 1-71% work completed. Package 2-Work retendered with due date on 07-03-2023. One offer received from M/s Nobletech, Documents to be submitted for prequalification. Package 3-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 4-Estimate is ready. Awaiting for approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which under consideration of KIIFB. Package 5-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Package 6-Work retendered with due date on 07-03-2023. Since no offer received extended upto 20-03-2023. Alappuzha KIIFB - AEE 1
24 Jan 2023 Package 1-68% work completed. Construction of 12LL OHSR at KATTOOR in Mararilkulam South Panchayat -Painting is progressing. Construction of 16LL OHSR at VADIKADU-. Painting is progressing. Construction of 16LL OHSR at CHATHANAD - Work completed upto side wall of Sump. Laying of clear water pumping main from Kulamakki to Kattoor OHSR progressing - 1233.800 mtrs(Total 2800 mtrs). CF Pump sets Supplied. Package 2,3,5 and 6 Work tendered several times with designs from WASCON and CET and with re casted estimate in PRICE 3.0. But no response. KIIFB instructed to tender the after approval of additional financial sanction. Package 4-Estimate is ready. Awaiting for approval of revised AS for additional financial sanction of RS. 87.30 Crores from KIIFB for tendering, which under consideration of KIIFB. Alappuzha KIIFB - AEE 1
23 Jan 2023 Package 1-68% work completed. Construction of 12LL OHSR at KATTOOR in Mararilkulam South Panchayat -Painting is progressing. Construction of 16LL OHSR at VADIKADU-. Painting is progressing. Construction of 16LL OHSR at CHATHANAD - Work completed upto side wall of Sump. Laying of clear water pumping main from Kulamakki to Kattoor OHSR progressing - 1233.800 mtrs(Total 2800 mtrs). CF Pump sets Supplied. Package 2,3,5 and 6 Work tendered several times. But no response. KIIFB instructed to tender the after approval of additional financial sanction. Package 4-Estimate is ready. Awaiting for revised AS approval from KIIFB for tendering, which under consideration of KIIFB. Alappuzha KIIFB - EE