| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Aug 2023 | GLSR Tank steining completed. | Kalpetta PH Sn 2 - AE | |
| 05 Aug 2023 | GLSR Tank first and second steining completed. | Kalpetta PH Sn 2 - AE | |
| 03 Aug 2023 | Foundation completed. | Kalpetta PH Sn 2 - AE | |
| 01 Aug 2023 | Site clearence and earthwork completed. | Kalpetta PH Sn 2 - AE | |
| 31 Jul 2023 | Site handed over. Order placed for materials. | Kalpetta PH Sn 2 - AE | |
| 29 Jul 2023 | Site handed over. Order placed for materials. | Kalpetta PH Sn 2 - AE | |
| 25 Jul 2023 | Site handed over. Order placed for materials. | Kalpetta PH Sn 2 - AE | |
| 22 Jul 2023 | Site handed over. Order placed for materials. | Kalpetta PH Sn 2 - AE | |
| 19 Jul 2023 | Site handed over. Order placed for materials. | Sulthan Bathery PH Dn EE | |
| 10 Jul 2023 | Site handed over. Order placed for materials. | Sulthan Bathery PH Dn EE |