| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Oct 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 05 Oct 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 03 Oct 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 30 Sep 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 27 Sep 2023 | Pipeline work in progress. | Sulthan Bathery PH Dn EE | |
| 19 Sep 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 16 Sep 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 13 Sep 2023 | Pipeline work in progress. | Kalpetta PH Sn 2 - AE | |
| 11 Sep 2023 | Pump house work completed. | Kalpetta PH Sn 2 - AE | |
| 07 Sep 2023 | Pump house work completed. | Kalpetta PH Sn 2 - AE |