02 Sep 2023 | *PCC works For demolished Pavements* 1) Pandarakandam = 42.6m | Kattakkada WS Sn AE | |
01 Sep 2023 | *PCC works For demolished Pavements* 1)chamavila = 73.5m | Kattakkada WS Sn AE | |
31 Aug 2023 | *PCC works For demolished Pavements* 1)Nediyavila - Lekshmi Nagar line, 2 = 47.7m | Kattakkada WS Sn AE | |
26 Aug 2023 | *Pipe layed,75mm,8kgf/cc - 18 m* 1)Ward 7,kunnuvila - 18 m | Kattakkada WS Sn AE | |
25 Aug 2023 | *FHTC provided - 02 No's* 1)Ward 7, kunnuvila - 02 No's *Pipe layed,75mm,8kgf/cc - 48 m* 1)Ward 7,kunnuvila - 48 m | Kattakkada WS Sn AE | |
24 Aug 2023 | *FHTC provided - 04 No's* 1)Ward 15, kutarakavu - 02 No's 2)Ward 8, velivilakam - 02 No's | Kattakkada WS Sn AE | |
23 Aug 2023 | *FHTC provided - 06 No's* 1)Ward 15, vizhavoor - 04 No's 2)Ward 8, velivilakam - 02 No's | Kattakkada WS Sn AE | |
22 Aug 2023 | *FHTC provided - 05 No's* 1)Ward 15, vizhavoor - 03 No's 2)Ward 1, thakidiyil - 02 No's | Kattakkada WS Sn AE | |
21 Aug 2023 | *FHTC provided - 07 No's* 1)Ward 7, velivilakam - 02 No's 2)Ward 6, pavachakuzhi - 03 No's 3)Ward 12, moolaman - 2 No's *Pipe layed,75mm,8kgf/cc - 168 m* 1)Ward 7,velivilakam - 66 m 2)Ward 6, pavachakuzhi 102 m | Kattakkada WS Sn AE | |
19 Aug 2023 | *FHTC provided - 10 No's* 1)Ward 06, Kunnuvila - 03 No's 2)Ward 02, Kundaman Bhagam - 03 No's 3)Ward 07, Velivilakam- 03 No's 4)Ward 09, Kunnuvila - 01 No's *Pipe layed,75mm,8kgf/cc - 68 m* 1)Ward 07, Velivilakam- 54m 2)Ward 09, Kunnuvila - 14m | Kattakkada WS Sn AE |