Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Oct 2023 | Pipe layed,75mm,8kg/cc- 54 m Ward 14, Vizhavoor CSI Church road - 54 m | Neyyattinkara WS Dn EE | |
12 Oct 2023 | On going | Neyyattinkara WS Dn EE | |
11 Oct 2023 | FHTC provided - 04 No's 1)Ward 10, Nalamkallu - 03 Nos. 2)Ward 03, Chathrakadavu - 01 Nos. Pipe layed, 75mm, 8kg/cc- 21 m 1) Ward 10, Nalamkallu- 15 m 2) Ward 03, Chathrakadavu - 6 m | Neyyattinkara WS Dn EE | |
10 Oct 2023 | Pipe layed, 75mm, 8kg/cc- 28 m 1) Ward 10, Nalamkallu- 28m | Neyyattinkara WS Dn EE | |
09 Oct 2023 | FHTC provided - 04 No's 1)Ward 9,kombetty-04 Nos. Pipe layed, 75mm, 8kg/cc- 36 m 1) Ward 10, Nalamkallu- 36m | Neyyattinkara WS Dn EE | |
07 Oct 2023 | On going | Neyyattinkara WS Dn EE | |
06 Oct 2023 | On going | Neyyattinkara WS Dn EE | |
05 Oct 2023 | On going | Neyyattinkara WS Dn EE | |
04 Oct 2023 | On going | Neyyattinkara WS Dn EE | |
03 Oct 2023 | On going | Neyyattinkara WS Dn EE |