| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Sep 2022 | Completed | Kollam QC AE | |
| 01 Sep 2022 | Completed | Kollam QC AE | |
| 17 Jun 2022 | All work bacteriology and physical-chemical area completed | Kollam QC AE | |
| 07 Apr 2022 | Work Completed | Kollam QC AE | |
| 18 Mar 2022 | Titration table work , AC fitting and cupboards work on going | Kollam QC AE | |
| 04 Mar 2022 | Partition work completed finishing work nin progress | Kollam QC AE | |
| 25 Feb 2022 | Partition work ongoing tile and false ceiling work finished | Kollam QC AE | |
| 28 Jan 2022 | Plumbing work is ongoing. Electrical work completed. Tile demolishing completed, tile paving in progress. False ceiling light fitting in progress. | Kollam QC AE | |
| 18 Jan 2022 | Slab work completed, electrical, false ceiling work is ongoing, tile demolishing work is ongoing. | Kollam QC AE | |
| 10 Jan 2022 | Work on progress, false ceiling, electrical work and slab work ongoing | Kollam QC AE |