Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Nov 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 1566 m, 90 mm 10 Kg/Cm2- 2710 m, 75 mm 10 Kg/Cm2- 771 m, 50 mm 10 Kg/Cm2- 396 m Kolachery PH Sn AE
14 Nov 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 1566 m, 90 mm 10 Kg/Cm2- 1864 m, 75 mm 10 Kg/Cm2- 771 m, 50 mm 10 Kg/Cm2- 198 m Kolachery PH Sn AE
11 Nov 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 666 m, 90 mm 10 Kg/Cm2- 1072 m, 75 mm 10 Kg/Cm2- 327 m, 50 mm 10 Kg/Cm2- 72 m Kolachery PH Sn AE
11 Nov 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 666 m, 90 mm 10 Kg/Cm2- 1072 m, 75 mm 10 Kg/Cm2- 327 m, 50 mm 10 Kg/Cm2- 72 m Kolachery PH Sn AE
06 Nov 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 666 m, 90 mm 10 Kg/Cm2- 1072 m, 75 mm 10 Kg/Cm2- 327 m, 50 mm 10 Kg/Cm2- 72 m Kolachery PH Sn AE
29 Oct 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 666 m, 90 mm 10 Kg/Cm2- 1072 m, 75 mm 10 Kg/Cm2- 327 m, 50 mm 10 Kg/Cm2- 72 m Kolachery PH Sn AE
26 Oct 2024 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 330 m, 90 mm 10 Kg/Cm2- 1072 m, 75 mm 10 Kg/Cm2- 327 m, 50 mm 10 Kg/Cm2- 72 m Kolachery PH Sn AE
23 Oct 2024 90 mm 10 Kg/Cm2- 852 m, 75 mm 10 Kg/Cm2- 312 m, 50 mm 10 Kg/Cm2- 66 m Kolachery PH Sn AE
21 Oct 2024 Not started Kolachery PH Sn AE
19 Oct 2024 Not started Kolachery PH Sn AE