| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Dec 2024 | 140 mm 10 Kg/cm2 - 306 m ,110 mm 10 Kg/Cm2- 1878 m, 90 mm 10 Kg/Cm2-3328m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 6 Nos | Kolachery PH Sn AE | |
| 16 Dec 2024 | 140 mm 10 Kg/cm2 - 306 m ,110 mm 10 Kg/Cm2- 1878 m, 90 mm 10 Kg/Cm2-3328m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 6 Nos | Kolachery PH Sn AE | |
| 12 Dec 2024 | 140 mm 10 Kg/cm2 - 306 m ,110 mm 10 Kg/Cm2- 1878 m, 90 mm 10 Kg/Cm2-3328m, 75 mm 10 Kg/Cm2- 2643 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 6 Nos | Kolachery PH Sn AE | |
| 09 Dec 2024 | 140 mm 10 Kg/cm2 - 306 m ,110 mm 10 Kg/Cm2- 1878 m, 90 mm 10 Kg/Cm2-3328m, 75 mm 10 Kg/Cm2- 2379 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m, FHTC- 1 No | Kolachery PH Sn AE | |
| 06 Dec 2024 | 140 mm 10 Kg/cm2 - 222 m ,110 mm 10 Kg/Cm2- 1986 m, 90 mm 10 Kg/Cm2-3058 m, 75 mm 10 Kg/Cm2- 1635 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m | Kolachery PH Sn AE | |
| 03 Dec 2024 | 140 mm 10 Kg/cm2 - 222 m ,110 mm 10 Kg/Cm2- 1986 m, 90 mm 10 Kg/Cm2-3058 m, 75 mm 10 Kg/Cm2- 1635 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m | Kolachery PH Sn AE | |
| 30 Nov 2024 | 140 mm 10 Kg/cm2 - 222 m ,110 mm 10 Kg/Cm2- 1986 m, 90 mm 10 Kg/Cm2-3058 m, 75 mm 10 Kg/Cm2- 1635 m, 63 mm 10 Kg/Cm2-120 m, 50 mm 10 Kg/Cm2- 492 m | Kolachery PH Sn AE | |
| 26 Nov 2024 | 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 1866 m, 90 mm 10 Kg/Cm2-3058 m, 75 mm 10 Kg/Cm2- 1479 m, 50 mm 10 Kg/Cm2- 396 m | Kolachery PH Sn AE | |
| 22 Nov 2024 | 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 1566 m, 90 mm 10 Kg/Cm2- 2944 m, 75 mm 10 Kg/Cm2- 1209m, 50 mm 10 Kg/Cm2- 396 m | Kolachery PH Sn AE | |
| 22 Nov 2024 | 140 mm 10 Kg/cm2 - 24 m ,110 mm 10 Kg/Cm2- 1566 m, 90 mm 10 Kg/Cm2- 2710 m, 75 mm 10 Kg/Cm2- 771 m, 50 mm 10 Kg/Cm2- 396 m | Kolachery PH Sn AE |