| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Oct 2025 | removing shutter | Kottarakkara PH Sn - AE | |
| 08 Oct 2025 | removing shutter | Kottarakkara PH Sn - AE | |
| 06 Oct 2025 | removing shutter | Kottarakkara PH Sn - AE | |
| 02 Oct 2025 | curing | Kottarakkara PH Sn - AE | |
| 29 Sep 2025 | Plastering third floor | Kottarakkara PH Sn - AE | |
| 26 Sep 2025 | Plastering second floor | Kottarakkara PH Sn - AE | |
| 23 Sep 2025 | Plastering second floor | Kottarakkara PH Sn - AE | |
| 20 Sep 2025 | Plastering second floor | Kottarakkara PH Sn - AE | |
| 17 Sep 2025 | curing | Kottarakkara PH Sn - AE | |
| 15 Sep 2025 | curing | Kottarakkara PH Sn - AE |