| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Feb 2025 | fourth floor ,tank bottom beam | Kottarakkara PH Sn - AE | |
| 18 Feb 2025 | fourth floor ,tank bottom beam | Kottarakkara PH Sn - AE | |
| 11 Feb 2025 | above third floor stair concrete | Kottarakkara PH Sn - AE | |
| 03 Feb 2025 | above third floor stair shuttering | Kottarakkara PH Sn - AE | |
| 01 Feb 2025 | above third floor stair shuttering | Kottarakkara PH Sn - AE | |
| 31 Jan 2025 | column concrete curing | Kottarakkara PH Sn - AE | |
| 29 Jan 2025 | column concrete curing | Kottarakkara PH Sn - AE | |
| 27 Jan 2025 | column concrete curing | Kottarakkara PH Sn - AE | |
| 25 Jan 2025 | column concrete curing | Kottarakkara PH Sn - AE | |