| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Oct 2023 | Out of 369 / 369 nos public tap disconnection completed. Concrete work (dismantling and demolishing portion) work 100 % completed | Sasthamcotta WS Sn 1 - AE | |
| 13 Oct 2023 | Out of 369 / 369 nos public tap disconnection completed. Concrete work (dismantling and demolishing portion) work 100 % completed | Sasthamcotta WS Sn 1 - AE | |
| 11 Oct 2023 | Out of 369 / 369 nos public tap disconnection completed. Concrete work (dismantling and demolishing portion) work in progress | Sasthamcotta WS Sn 1 - AE | |
| 09 Oct 2023 | Out of 369 / 369 nos public tap disconnection completed. Concrete work (dismantling and demolishing portion) work in progress | Sasthamcotta WS Sn 1 - AE | |
| 27 Sep 2023 | Out of 369 / 356 nos public tap disconnection completed | Sasthamcotta WS Sn 1 - AE | |
| 24 Sep 2023 | Out of 369 / 356 nos public tap disconnection completed | Sasthamcotta WS Sn 1 - AE | |
| 31 Aug 2023 | Out of 369 / 180 nos of public tap disconnection completed | Sasthamcotta WS Sn 1 - AE |