16 Mar 2024 160mm PVC 510m layed, 140mm PVC 726m layed & 90mm PVC - 895.20m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
14 Mar 2024 160mm PVC 510m layed, 140mm PVC 726m layed & 90mm PVC - 895.20m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
11 Mar 2024 160mm PVC 510m layed & 140mm PVC 528m layed, 90mm PVC -555.2m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
11 Mar 2024 160mm PVC 510m layed & 140mm PVC 528m layed, 90mm PVC -108m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
06 Mar 2024 160mm PVC 510m layed & 140mm PVC 528m layed, 90mm PVC -108m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
01 Mar 2024 160mm PVC 510m layed & 140mm PVC 432m layed, 90mm PVC -108m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:167. Mallappally PH Sn - AE
27 Feb 2024 160mm PVC 510m layed & 140mm PVC 432m layed, 90mm PVC -108m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:133. Mallappally PH Sn - AE
23 Feb 2024 160mm PVC 510m layed & 140mm PVC 432m layed,90mm PVC -108m layed.Total No.of connections gived:268 connections.No.of Connections Geo tagged& IMIS Completed:133. Mallappally PH Sn - AE
20 Feb 2024 160mm PVC 510m layed & 140mm PVC 432m layed,90mm PVC -108m layed.Total No.of connections gived:268 connections.No.of Connections Geo tagged& IMIS Completed:133. Mallappally PH Sn - AE
15 Feb 2024 160mm PVC 510m layed & 140mm PVC 432m layed,90mm PVC -108m layed.Total No.of connections gived:268 connections.No.of Connections Geo tagged& IMIS Completed:126. Mallappally PH Sn - AE