| Thaliparamba WS Section |
| Date: 15/10/2025 |
Work has been completed | 100% Completed
work completed
| Thaliparamba WS Section |
| Date: 01/08/2025 |
Work has been completed | 100% Completed
Work completed
| Thaliparamba WS Sub Dn |
| Date: 27/06/2025 |
Work in progress | 93% Completed
25 HP & 5HP Submersible and open well pump set are supplied and fixed , 125 mm GI & 65 mm Gi Pumping main work completed. desilting of well completed.Distribution going on
| Thaliparamba WS Section |
| Date: 19/06/2025 |
Work in progress | 92% Completed
25 HP & 5HP Submersible and open well pump set are supplied and fixed , 125 mm GI & 65 mm Gi Pumping main work completed. desilting of well completed
| Thaliparamba WS Section |
| Date: 30/04/2025 |
Work in progress | 85% Completed
OHSR Painting work completed.
| Thaliparamba WS Section |
| Date: 05/12/2024 |
Work in progress | 52% Completed
OHSR's structural work completed
| Thaliparamba WS Section |
| Date: 26/11/2024 |
Work in progress | 52% Completed
OHSR's structural work completed
| Thaliparamba WS Section |
| Date: 20/11/2024 |
Work in progress | 50% Completed
OHSR's roof slab completed
| Thaliparamba WS Section |
| Date: 30/10/2024 |
Work in progress | 45% Completed
Tank wall up to bottom of roof slab completed
| Thaliparamba WS Section |
| Date: 10/10/2024 |
Work in progress | 42% Completed
Tank wall up to 2meter completed
| Thaliparamba WS Section |
| Date: 07/09/2024 |
Work in progress | 40% Completed
RCC work of deck beam, deck slab and wall up to haunch completed
| Thaliparamba WS Section |
| Date: 31/08/2024 |
Work in progress | 35% Completed
RCC work completed up to bottom of Deck beam
| Thaliparamba WS Section |
| Date: 28/08/2024 |
Work in progress | 20% Completed
RCC work completed up to second brace beam
| Thaliparamba WS Section |
| Date: 30/07/2024 |
Work in progress | 10% Completed
RCC work completed up to First brace beam
| Thaliparamba WS Section |
| Date: 29/06/2024 |
Work in progress | 5% Completed
RCC foundation footing of OHSR completed
| Thaliparamba WS Section |
| Date: 17/06/2024 |
Work in progress | 1% Completed
OHSR's foundation earth work completed
| Thaliparamba WS Section |
| Date: 15/06/2024 |
Work in progress | 0% Completed
site handover
| Thaliparamba WS Section |
| Date: 10/06/2024 |
Work in progress | 0% Completed
agreement executed
| Thaliparamba WS Dn EE |
| Date: 16/03/2024 |
Work has started | 0% Completed
Work order issued.