| Project | KANNUR DISTRICT PANCHAYATH-ARRANGEMENTS OF DRINKING WATER FACILITY TO MAJOR AREAS IN DISTRICT AGRICULTURAL FARM IN KARIMBAM-General Civil Work |
|---|---|
| Project Code | KNRDEPO032216921P1 |
| Type | Package |
| Main Project | DEPOSIT-KANNUR DISTRICT PANCHAYATH-ARRANGEMENTS OF DRINKING WATER FACILITY TO MAJOR AREAS IN DISTRICT AGRICULTURAL FARM IN KARIMBAM-General Civil Work. |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | KANNUR DISTRICT PANCHAYATH-ARRANGEMENTS OF DRINKING WATER FACILITY TO MAJOR AREAS IN DISTRICT AGRICULTURAL FARM IN KARIMBAM-General Civil Work. |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 9706000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/21763/2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/06/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Dec 2024 |
| Expected date of Completion | 14/12/2024 |
| TS Date | 16 Nov 2023 |
|---|---|
| Tender Closing | 29 Nov 2023 |
| Price bid opening | 30 Nov 2023 |
| Workorder Date | 16 Mar 2024 |
|---|---|
| NA | 10 Jun 2024 |
| Thaliparamba WS Section |
| Date: 15/10/2025 |
Work has been completed | 100% Completed
work completed.
| Thaliparamba WS Section |
| Date: 01/08/2025 |
Work has been completed | 100% Completed
Work completed.