| Thrissur PH Dn EE |
| Date: 09/11/2021 |
Work has started | 0% Completed
Request letter given to Secretary, Thrissur corporation for road cutting permission on 27.7.2018, 29.112019, 30.12.2020, 9.2.2021 but it is not received. Letter given to District Collector, Thrissur for interferring in this for getting road cutting permission on 27.7.2018.Permission not received and hence work dropped. Work terminated on 24.02.2021. Alternate proposal Submitted through JJM phase II
| Thrissur WW Sn - AE 2 |
| Date: 08/11/2021 |
Work in progress | 5% Completed
work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II
| Thrissur PH Dn EE |
| Date: 02/06/2021 |
Work in progress | 5% Completed
work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II
| Thrissur PH Dn EE |
| Date: 01/06/2021 |
Work in progress | 5% Completed
work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II
| Thrissur PH Dn EE |
| Date: 25/03/2021 |
Work in progress | 5% Completed
Work cancelled as road cutting sanction from PWD/Corporation not obtained
| Thrissur PH Dn EE |
| Date: 24/03/2021 |
Work has started | 0% Completed
Work cancelled as road cutting sanction from PWD/Corporation not obtained
| Thrissur PH Dn EE |
| Date: 22/02/2021 |
Work in progress | 5% Completed
Request letter to Secretary, Thrissur corporation for road cutting permission on 27.7.2018, 29.112019, 30.12.2020, 9.2.2021 but not received till date. Request letter to District Collector, Thrissur for corporation road cutting permission on 27.7.2018 Contractor requested to terminate the work.