Thrissur PH Dn EE
Date: 09/11/2021

Work has started | 0% Completed

Request letter given to Secretary, Thrissur corporation for road cutting permission on 27.7.2018, 29.112019, 30.12.2020, 9.2.2021 but it is not received. Letter given to District Collector, Thrissur for interferring in this for getting road cutting permission on 27.7.2018.Permission not received and hence work dropped. Work terminated on 24.02.2021. Alternate proposal Submitted through JJM phase II

Thrissur WW Sn - AE 2
Date: 08/11/2021

Work in progress | 5% Completed

work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II

Thrissur PH Dn EE
Date: 02/06/2021

Work in progress | 5% Completed

work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II

Thrissur PH Dn EE
Date: 01/06/2021

Work in progress | 5% Completed

work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II

Thrissur PH Dn EE
Date: 25/03/2021

Work in progress | 5% Completed

Work cancelled as road cutting sanction from PWD/Corporation not obtained

Thrissur PH Dn EE
Date: 24/03/2021

Work has started | 0% Completed

Work cancelled as road cutting sanction from PWD/Corporation not obtained

Thrissur PH Dn EE
Date: 22/02/2021

Work in progress | 5% Completed

Request letter to Secretary, Thrissur corporation for road cutting permission on 27.7.2018, 29.112019, 30.12.2020, 9.2.2021 but not received till date. Request letter to District Collector, Thrissur for corporation road cutting permission on 27.7.2018 Contractor requested to terminate the work.