| Project | State Plan 2015 -16 - 19 Replacement of old and damaged pipes -RWSS Adat -Replacing the existing gravity main with DI-K9 -200mm from Chaithanya junction Thrissur to Puzhakkal Sump |
|---|---|
| Project Code | TCRGOI09151775P1 |
| Type | Package |
| Main Project | State Plan 2015 -16 - 19 Replacement of old and damaged pipes -RWSS Adat -Replacing the existing gravity main with DI-K9 -200mm from Chaithanya junction Thrissur to Puzhakkal Sump |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | 19 Replacement of old and damaged pipes -RWSS Adat -Replacing the existing gravity main with DI-K9 -200mm from Chaithanya junction Thrissur to Puzhakkal Sump |
| Status | Dropped |
| District | Thrissur |
| Executing Office | Thrissur WW Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 19400000 |
| TS Number | |
| Technical specification | 19 Replacement of old and damaged pipes |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/11/2016 |
|---|---|
| Scheduled date of Completion as per agreement | 04 Apr 2017 |
| Expected date of Completion | 31/05/2021 |
| TS Date | 07 Jan 2016 |
|---|
| Thrissur PH Dn EE |
| Date: 09/11/2021 |
Work has started | 0% Completed
Request letter given to Secretary, Thrissur corporation for road cutting permission on 27.7.2018, 29.112019, 30.12.2020, 9.2.2021 but it is not received. Letter given to District Collector, Thrissur for interferring in this for getting road cutting permission on 27.7.2018.Permission not received and hence work dropped. Work terminated on 24.02.2021. Alternate proposal Submitted through JJM phase II.
| Thrissur WW Sn - AE 2 |
| Date: 08/11/2021 |
Work in progress | 5% Completed
work terminated on 24.02.2021 . Alternate proposal Submitted through JJM phase II .