Perlasserry Sn 1
Date: 02/07/2025

Work in progress | 64% Completed

Pipe laying completed(2 kms)

Perlasserry Sn 1
Date: 28/06/2025

Work in progress | 63% Completed

pipe laying completed (2km)

Perlasserry Sn 1
Date: 24/06/2025

Work in progress | 60% Completed

pipe laying completed (2km)

Perlasserry Sn 1
Date: 17/06/2025

Work in progress | 53% Completed

Work started, 80% laying completed.

Perlasserry Sn 1
Date: 27/05/2025

Work in progress | 53% Completed

Work started, 80% laying completed.

Perlasserry Sn 1
Date: 16/05/2025

Work in progress | 50% Completed

Work started, 75% laying completed.

Perlasserry Sn 1
Date: 07/05/2025

Work in progress | 45% Completed

Work started, 70% laying completed.

Perlasserry Sn 1
Date: 29/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 19/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 15/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 10/04/2025

Work in progress | 35% Completed

Work started, 48% laying completed.

Perlasserry Sn 1
Date: 01/04/2025

Work in progress | 30% Completed

Work started, 45% laying completed.

Perlasserry Sn 1
Date: 24/03/2025

Work in progress | 25% Completed

Work started ,and 40% laying completed.

Perlasserry Sn 1
Date: 17/03/2025

Work in progress | 15% Completed

Work started ,excavation 20% completed.

Perlasserry Sn 1
Date: 27/02/2025

Work has started | 0% Completed

LOA issued. PBG submitted for restoration fee ,road cutting permission pending.

Perlasserry Sn 1
Date: 12/02/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 01/02/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 28/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 25/01/2025

Work in progress | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 18/01/2025

Work in progress | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 13/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 04/01/2025

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 31/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 21/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 17/12/2024

Work has started | 0% Completed

LOA issued. COP submitted ,road cutting permission pending.

Perlasserry Sn 1
Date: 10/12/2024

Work has started | 0% Completed

LOA issued. Road cutting permission and pipe testing pending.

Kannur PH Dn EE
Date: 28/11/2024

Work has started | 0% Completed

LOA Issued.

Kannur PH Dn EE
Date: 18/11/2024

Work has started | 0% Completed

LOA issued on 08-11-2024.

Perlasserry Sn 1
Date: 13/11/2024

Work has started | 0% Completed

Tender under scrutiny

Perlasserry Sn 1
Date: 07/11/2024

Work has started | 0% Completed

Tender under scrutiny

Kannur PH Dn EE
Date: 02/11/2024

Work has started | 0% Completed

2 response received. Tender under scrutiny.

Perlasserry Sn 1
Date: 28/10/2024

Work has started | 0% Completed

No response , work retendered with due date 28.10.2024

Perlasserry Sn 1
Date: 22/10/2024

Work has started | 0% Completed

No response , work retendered with due date 28.10.2024

Perlasserry Sn 1
Date: 18/10/2024

Work has started | 0% Completed

No response, work retendered.

Kannur PH Dn EE
Date: 14/10/2024

Work has started | 0% Completed

No response, work retendered.

Kannur PH Dn EE
Date: 04/10/2024

Work has started | 0% Completed

Work Retendered.

Kannur PH Dn EE
Date: 27/09/2024

Work has started | 0% Completed

Work Retendered.

Kannur PH Dn EE
Date: 24/09/2024

Work has started | 0% Completed

Single offer received. Work to be retendered.

Kannur PH Dn EE
Date: 19/09/2024

Work has started | 0% Completed

Single offer received. Work to be retendered.

Perlasserry Sn 1
Date: 11/09/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 05/09/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 29/08/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 23/08/2024

Work has started | 0% Completed

Estimate submitted to SE.

Kannur PH Dn EE
Date: 14/08/2024

Work has started | 0% Completed

AS Accorded on 06-08-2024, work to be tendered.