Perlasserry Sn 1 |
Date: 02/07/2025 |
Work in progress | 64% Completed
Pipe laying completed(2 kms)
Perlasserry Sn 1 |
Date: 28/06/2025 |
Work in progress | 63% Completed
pipe laying completed (2km)
Perlasserry Sn 1 |
Date: 24/06/2025 |
Work in progress | 60% Completed
pipe laying completed (2km)
Perlasserry Sn 1 |
Date: 17/06/2025 |
Work in progress | 53% Completed
Work started, 80% laying completed.
Perlasserry Sn 1 |
Date: 27/05/2025 |
Work in progress | 53% Completed
Work started, 80% laying completed.
Perlasserry Sn 1 |
Date: 16/05/2025 |
Work in progress | 50% Completed
Work started, 75% laying completed.
Perlasserry Sn 1 |
Date: 07/05/2025 |
Work in progress | 45% Completed
Work started, 70% laying completed.
Perlasserry Sn 1 |
Date: 29/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
Perlasserry Sn 1 |
Date: 19/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
Perlasserry Sn 1 |
Date: 15/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
Perlasserry Sn 1 |
Date: 10/04/2025 |
Work in progress | 35% Completed
Work started, 48% laying completed.
Perlasserry Sn 1 |
Date: 01/04/2025 |
Work in progress | 30% Completed
Work started, 45% laying completed.
Perlasserry Sn 1 |
Date: 24/03/2025 |
Work in progress | 25% Completed
Work started ,and 40% laying completed.
Perlasserry Sn 1 |
Date: 17/03/2025 |
Work in progress | 15% Completed
Work started ,excavation 20% completed.
Perlasserry Sn 1 |
Date: 27/02/2025 |
Work has started | 0% Completed
LOA issued. PBG submitted for restoration fee ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 12/02/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 01/02/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 28/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 25/01/2025 |
Work in progress | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 18/01/2025 |
Work in progress | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 13/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 04/01/2025 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 31/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 21/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 17/12/2024 |
Work has started | 0% Completed
LOA issued. COP submitted ,road cutting permission pending.
Perlasserry Sn 1 |
Date: 10/12/2024 |
Work has started | 0% Completed
LOA issued. Road cutting permission and pipe testing pending.
Kannur PH Dn EE |
Date: 28/11/2024 |
Work has started | 0% Completed
LOA Issued.
Kannur PH Dn EE |
Date: 18/11/2024 |
Work has started | 0% Completed
LOA issued on 08-11-2024.
Perlasserry Sn 1 |
Date: 13/11/2024 |
Work has started | 0% Completed
Tender under scrutiny
Perlasserry Sn 1 |
Date: 07/11/2024 |
Work has started | 0% Completed
Tender under scrutiny
Kannur PH Dn EE |
Date: 02/11/2024 |
Work has started | 0% Completed
2 response received. Tender under scrutiny.
Perlasserry Sn 1 |
Date: 28/10/2024 |
Work has started | 0% Completed
No response , work retendered with due date 28.10.2024
Perlasserry Sn 1 |
Date: 22/10/2024 |
Work has started | 0% Completed
No response , work retendered with due date 28.10.2024
Perlasserry Sn 1 |
Date: 18/10/2024 |
Work has started | 0% Completed
No response, work retendered.
Kannur PH Dn EE |
Date: 14/10/2024 |
Work has started | 0% Completed
No response, work retendered.
Kannur PH Dn EE |
Date: 04/10/2024 |
Work has started | 0% Completed
Work Retendered.
Kannur PH Dn EE |
Date: 27/09/2024 |
Work has started | 0% Completed
Work Retendered.
Kannur PH Dn EE |
Date: 24/09/2024 |
Work has started | 0% Completed
Single offer received. Work to be retendered.
Kannur PH Dn EE |
Date: 19/09/2024 |
Work has started | 0% Completed
Single offer received. Work to be retendered.
Perlasserry Sn 1 |
Date: 11/09/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
Kannur PH Dn EE |
Date: 05/09/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
Kannur PH Dn EE |
Date: 29/08/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
Kannur PH Dn EE |
Date: 23/08/2024 |
Work has started | 0% Completed
Estimate submitted to SE.
Kannur PH Dn EE |
Date: 14/08/2024 |
Work has started | 0% Completed
AS Accorded on 06-08-2024, work to be tendered.