State plan 2024-25 -Optimisation of Production and Transmission - Urgent Relaying of undersized and Frequently busting Pipe line in Vengad Angadi of Vengad panchayath-Laying of 110 mm & 140 mm PVC pipe -Pipeline Work

Project State plan 2024-25 -Optimisation of Production and Transmission - Urgent Relaying of undersized and Frequently busting Pipe line in Vengad Angadi of Vengad panchayath-Laying of 110 mm & 140 mm PVC pipe -Pipeline Work
Project Code KNRGOK082416253P1
Type Package
Main Project State plan 2024-25 -Optimisation of Production and Transmission - Urgent Relaying of undersized and Frequently busting Pipe line in Vengad Angadi of Vengad panchayath-Laying of 110 mm & 140 mm PVC pipe -Pipeline Work
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description State plan 2024-25 -Optimisation of Production and Transmission - Urgent Relaying of undersized and Frequently busting Pipe line in Vengad Angadi of Vengad panchayath-Laying of 110 mm & 140 mm PVC pipe -Pipeline Work
Status On-going
District Kannur
Executing Office Perlassery Sn 1
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perlasserry Sn 1
Date: 02/07/2025

Work in progress | 64% Completed

Pipe laying completed(2 kms).

Perlasserry Sn 1
Date: 28/06/2025

Work in progress | 63% Completed

pipe laying completed (2km).