Mattannur WS Sn
Date: 30/06/2025

Work in progress | 34% Completed

FHTCs started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain

Mattannur WS Sn
Date: 18/06/2025

Work in progress | 34% Completed

FHTC providing started - 2281 Nos; Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr work held up due to heavy rain

Mattannur WS Sn
Date: 14/05/2025

Work in progress | 21% Completed

FHTC providing started - 1021 Nos Pipe line laid - 12300mtr

Mattannur WS Sn
Date: 30/04/2025

Work in progress | 21% Completed

FHTC providing started - 1021 Nos Pipe line laid - 12300mtr

Mattannur WS Sn
Date: 16/04/2025

Work in progress | 21% Completed

FHTC providing started - 1021 Nos Pipe line laid - 12300mtr

Mattannur WS Sn
Date: 01/04/2025

Work in progress | 21% Completed

FHTC providing started - 1021 Nos Pipe line laid - 12300mtr

Mattannur WS Sn
Date: 16/03/2025

Work in progress | 21% Completed

FHTC providing started - 1021 Nos Pipe line laid - 12300mtr

Mattannur WS Sn
Date: 07/03/2025

Work in progress | 14% Completed

FHTC providing started - 824 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 25/02/2025

Work in progress | 14% Completed

FHTC providing started - 824 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 11/02/2025

Work in progress | 14% Completed

FHTC providing started - 824 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 28/01/2025

Work in progress | 14% Completed

FHTC providing started - 824 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 20/01/2025

Work in progress | 12% Completed

FHTC providing started - 824 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 12/01/2025

Work in progress | 12% Completed

FHTC providing started - 678 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 06/01/2025

Work in progress | 11% Completed

FHTC providing started - 569 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 01/01/2025

Work in progress | 11% Completed

FHTC providing started - 498 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 26/12/2024

Work in progress | 10% Completed

FHTC providing started - 341 Nos Pipe line laid - 8400mtr

Mattannur WS Sn
Date: 18/12/2024

Work in progress | 2% Completed

FHTC providing started - 167Nos

Mattannur WS Sn
Date: 12/12/2024

Work in progress | 2% Completed

FHTC providing started - 167Nos

Mattannur WS Sn
Date: 03/12/2024

Work in progress | 2% Completed

FHTC providing started - 167Nos

Mattannur WS Sn
Date: 25/11/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 18/11/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 11/11/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 04/11/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 28/10/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 21/10/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 16/10/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 03/10/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 27/09/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 17/09/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 05/09/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 21/08/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 06/08/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 31/07/2024

Work has started | 0% Completed

work not started

Mattannur WS Sn
Date: 22/07/2024

Work has started | 0% Completed

work not started

Kannur PH Dn EE
Date: 18/07/2024

Work has started | 0% Completed

Not started