| Mattannur WS Sn |
| Date: 08/01/2026 |
Work in progress | 44% Completed
pipe laying and road restoration work in progress
| Mattannur WS Sn |
| Date: 06/01/2026 |
Work in progress | 44% Completed
pipe laying and road restoration work in progress
| Mattannur WS Sn |
| Date: 29/12/2025 |
Work in progress | 44% Completed
pipe laying and road restoration work in progress
| Mattannur WS Sn |
| Date: 20/12/2025 |
Work in progress | 44% Completed
pipe laying and road restoration work in progress
| Mattannur WS Sn |
| Date: 04/12/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 25/11/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 14/11/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 05/11/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 15/10/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 03/10/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 22/09/2025 |
Work in progress | 34% Completed
road restoration work in progress - 5410mtr completed
| Mattannur WS Sn |
| Date: 11/09/2025 |
Work in progress | 34% Completed
FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain
| Mattannur WS Sn |
| Date: 19/08/2025 |
Work in progress | 34% Completed
FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain
| Mattannur WS Sn |
| Date: 31/07/2025 |
Work in progress | 34% Completed
FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain
| Mattannur WS Sn |
| Date: 21/07/2025 |
Work in progress | 34% Completed
FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain
| Mattannur WS Sn |
| Date: 30/06/2025 |
Work in progress | 34% Completed
FHTCs started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain
| Mattannur WS Sn |
| Date: 18/06/2025 |
Work in progress | 34% Completed
FHTC providing started - 2281 Nos; Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr work held up due to heavy rain
| Mattannur WS Sn |
| Date: 14/05/2025 |
Work in progress | 21% Completed
FHTC providing started - 1021 Nos Pipe line laid - 12300mtr
| Mattannur WS Sn |
| Date: 30/04/2025 |
Work in progress | 21% Completed
FHTC providing started - 1021 Nos Pipe line laid - 12300mtr
| Mattannur WS Sn |
| Date: 16/04/2025 |
Work in progress | 21% Completed
FHTC providing started - 1021 Nos Pipe line laid - 12300mtr
| Mattannur WS Sn |
| Date: 01/04/2025 |
Work in progress | 21% Completed
FHTC providing started - 1021 Nos Pipe line laid - 12300mtr
| Mattannur WS Sn |
| Date: 16/03/2025 |
Work in progress | 21% Completed
FHTC providing started - 1021 Nos Pipe line laid - 12300mtr
| Mattannur WS Sn |
| Date: 07/03/2025 |
Work in progress | 14% Completed
FHTC providing started - 824 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 25/02/2025 |
Work in progress | 14% Completed
FHTC providing started - 824 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 11/02/2025 |
Work in progress | 14% Completed
FHTC providing started - 824 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 28/01/2025 |
Work in progress | 14% Completed
FHTC providing started - 824 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 20/01/2025 |
Work in progress | 12% Completed
FHTC providing started - 824 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 12/01/2025 |
Work in progress | 12% Completed
FHTC providing started - 678 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 06/01/2025 |
Work in progress | 11% Completed
FHTC providing started - 569 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 01/01/2025 |
Work in progress | 11% Completed
FHTC providing started - 498 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 26/12/2024 |
Work in progress | 10% Completed
FHTC providing started - 341 Nos Pipe line laid - 8400mtr
| Mattannur WS Sn |
| Date: 18/12/2024 |
Work in progress | 2% Completed
FHTC providing started - 167Nos
| Mattannur WS Sn |
| Date: 12/12/2024 |
Work in progress | 2% Completed
FHTC providing started - 167Nos
| Mattannur WS Sn |
| Date: 03/12/2024 |
Work in progress | 2% Completed
FHTC providing started - 167Nos
| Mattannur WS Sn |
| Date: 25/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 11/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 04/11/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 28/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 27/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 17/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 05/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/08/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 06/08/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 31/07/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 22/07/2024 |
Work has started | 0% Completed
work not started
| Kannur PH Dn EE |
| Date: 18/07/2024 |
Work has started | 0% Completed
Not started