Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Munderi panchayath -Reappropriation - WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Munderi panchayath -Reappropriation - WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work
Project Code KNRJJM102316029P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Munderi panchayath -Reappropriation - WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Munderi panchayath -Reappropriation - WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs -Pipeline Work
Status On-going
District Kannur
Executing Office Mattannur PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 136300000
TS Number 21807/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 26 Nov 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 13 Dec 2023
Estimate Approval 13 Dec 2023
NIT Approval 22 Dec 2023
Tender Closing 03 Jan 2024
Price bid opening 04 Jan 2024

Approval Dates

Workorder Date 07 Feb 2024
NA 17 May 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur WS Sn
Date: 30/06/2025

Work in progress | 34% Completed

FHTCs started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain.

Mattannur WS Sn
Date: 18/06/2025

Work in progress | 34% Completed

FHTC providing started - 2281 Nos; Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr work held up due to heavy rain.