Mattannur WS Sn
Date: 30/06/2025

Work in progress | 74% Completed

pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain

Mattannur WS Sn
Date: 18/06/2025

Work in progress | 74% Completed

pipe laying work completed upto around 59Km, road restoration work is going on - 5347 mtr completed work held up due to rain

Mattannur WS Sn
Date: 16/06/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 14/05/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 30/04/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 16/04/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 01/04/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 16/03/2025

Work in progress | 53% Completed

pipe laying work is going on - 52 Km completed

Mattannur WS Sn
Date: 07/03/2025

Work in progress | 44% Completed

pipe laying work is going on - 44 Km completed

Mattannur WS Sn
Date: 25/02/2025

Work in progress | 44% Completed

pipe laying work is going on - 44 Km completed

Mattannur WS Sn
Date: 11/02/2025

Work in progress | 44% Completed

pipe laying work is going on - 44 Km completed

Mattannur WS Sn
Date: 28/01/2025

Work in progress | 44% Completed

pipe laying work is going on - 44 Km completed

Mattannur WS Sn
Date: 20/01/2025

Work in progress | 44% Completed

pipe laying work is going on - 44 Km completed

Mattannur WS Sn
Date: 12/01/2025

Work in progress | 42% Completed

pipe laying work is going on - 41 Km completed

Mattannur WS Sn
Date: 06/01/2025

Work in progress | 41% Completed

pipe laying work is going on - 40.5 Km completed

Mattannur WS Sn
Date: 01/01/2025

Work in progress | 40% Completed

pipe laying work is going on - 39Km completed

Mattannur WS Sn
Date: 26/12/2024

Work in progress | 40% Completed

pipe laying work is going on - 38km completed

Mattannur WS Sn
Date: 18/12/2024

Work in progress | 37% Completed

pipe laying work is going on

Mattannur WS Sn
Date: 12/12/2024

Work in progress | 37% Completed

pipe laying work is going on

Mattannur WS Sn
Date: 03/12/2024

Work in progress | 37% Completed

pipe laying work is going on

Mattannur WS Sn
Date: 25/11/2024

Work in progress | 37% Completed

21 km pipe laying work completed

Mattannur WS Sn
Date: 18/11/2024

Work in progress | 36% Completed

FHTC - 363 Nos, HTC - 105Nos, Pipe laying work in progresss

Mattannur WS Sn
Date: 11/11/2024

Work in progress | 34% Completed

FHTC - 363 Nos, HTC - 105Nos, Pipe laying work in progresss

Mattannur WS Sn
Date: 04/11/2024

Work in progress | 33% Completed

FHTC - 363 Nos, HTC - 105Nos

Mattannur WS Sn
Date: 28/10/2024

Work in progress | 30% Completed

FHTC - 315 Nos, HTC - 105Nos

Mattannur WS Sn
Date: 21/10/2024

Work in progress | 27% Completed

FHTC - 220 Nos, HTC - 105Nos

Mattannur WS Sn
Date: 16/10/2024

Work in progress | 27% Completed

FHTC - 218 Nos, HTC - 105Nos

Mattannur WS Sn
Date: 03/10/2024

Work in progress | 22% Completed

FHTC - 112Nos, HTC - 105Nos

Mattannur WS Sn
Date: 27/09/2024

Work in progress | 14% Completed

FHTC - 39, HTC - 105Nos

Mattannur WS Sn
Date: 17/09/2024

Work in progress | 12% Completed

FHTC - 25, HTC - 105Nos