| Aluva PH Dn EE |
| Date: 27/04/2021 |
Work has been completed | 100% Completed
completed
| Aluva PH Dn EE |
| Date: 26/04/2021 |
Work has been completed | 100% Completed
Completed
| Aluva PH Dn EE |
| Date: 23/04/2021 |
Work in progress | 80% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 22/04/2021 |
Work in progress | 79% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 21/04/2021 |
Work in progress | 79% Completed
79% Completed
| Aluva PH Dn EE |
| Date: 20/04/2021 |
Work in progress | 79% Completed
79% Completed
| Aluva PH Dn EE |
| Date: 19/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 17/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 16/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 15/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 13/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 12/04/2021 |
Work in progress | 79% Completed
On going
| Aluva PH Dn EE |
| Date: 09/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 08/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 07/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 05/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 03/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 01/04/2021 |
Work in progress | 78% Completed
On going
| Aluva PH Dn EE |
| Date: 31/03/2021 |
Work in progress | 78% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 30/03/2021 |
Work in progress | 78% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 29/03/2021 |
Work in progress | 23% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 27/03/2021 |
Work in progress | 23% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 26/03/2021 |
Work in progress | 23% Completed
Work in progress
| Aluva PH Dn EE |
| Date: 25/03/2021 |
Work in progress | 23% Completed
On going
| Aluva PH Dn EE |
| Date: 24/03/2021 |
Work in progress | 23% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 23/03/2021 |
Work in progress | 23% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 22/03/2021 |
Work in progress | 23% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 19/03/2021 |
Work in progress | 23% Completed
On going
| Aluva PH Dn EE |
| Date: 18/03/2021 |
Work in progress | 22% Completed
On going
| Aluva PH Dn EE |
| Date: 17/03/2021 |
Work in progress | 22% Completed
On going
| Aluva PH Dn EE |
| Date: 16/03/2021 |
Work in progress | 22% Completed
On going
| Aluva PH Dn EE |
| Date: 15/03/2021 |
Work in progress | 22% Completed
On going
| Aluva PH Dn EE |
| Date: 14/03/2021 |
Work in progress | 21% Completed
On going
| Aluva PH Dn EE |
| Date: 13/03/2021 |
Work in progress | 21% Completed
60 FHTCs completed
| Aluva PH Dn EE |
| Date: 08/03/2021 |
Work in progress | 3% Completed
On going
| Aluva PH Dn EE |
| Date: 06/03/2021 |
Work in progress | 3% Completed
On going
| Aluva PH Dn EE |
| Date: 05/03/2021 |
Work in progress | 3% Completed
On going
| Aluva PH Dn EE |
| Date: 03/03/2021 |
Work in progress | 3% Completed
on going
| Aluva PH Dn EE |
| Date: 01/03/2021 |
Work in progress | 3% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 23/02/2021 |
Work in progress | 3% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 20/02/2021 |
Work in progress | 3% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 18/02/2021 |
Work in progress | 3% Completed
Ongoing
| Aluva PH Dn EE |
| Date: 16/02/2021 |
Work has started | 0% Completed
WORK ORDER GIVEN
| Aluva PH Dn EE |
| Date: 28/12/2020 |
Work has started | 0% Completed
WORK ORDER GIVEN