| Project | J J M- PROVIDING FHTC TO RURAL HOUSE HOLDS IN CHENGAMANAD PANCHAYATH PART III (280 Nos) |
|---|---|
| Project Code | EKMJJM08203022P3 |
| Type | Package |
| Main Project | J J M- PROVIDING FHTC TO RURAL HOUSE HOLDS IN CHENGAMANAD PANCHAYATH |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | J J M- PROVIDING FHTC TO RURAL HOUSE HOLDS IN CHENGAMANAD PANCHAYATH PART III (280 Nos) |
| Status | On-going |
| District | Ernakulam |
| Executing Office | Kariyad PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 2700000 |
| TS Number | TS/52020-2021/2020/25306 |
| Technical specification | AS 146,3 L TS 27 L |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/01/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Nov 2021 |
| Expected date of Completion | 16/04/2021 |
| TS Date | 02 Nov 2020 |
|---|---|
| Estimate Approval | 02 Nov 2020 |
| NIT Approval | 02 Nov 2020 |
| Tender Closing | 10 Nov 2020 |
| Technichal Pre-Qualification | 02 Nov 2020 |
| Price bid opening | 13 Nov 2020 |
| Workorder Date | 07 Jan 2020 |
|---|---|
| NA | 21 Jan 2021 |
| Aluva PH Dn EE |
| Date: 27/04/2021 |
Work has been completed | 100% Completed
completed.
| Aluva PH Dn EE |
| Date: 26/04/2021 |
Work has been completed | 100% Completed
Completed.