Chavasseryparamba WS Sn AE |
Date: 16/09/2023 |
Work has been completed | 100% Completed
Work completed Bill submitted
Chavasseryparamba WS Sn AE |
Date: 12/09/2023 |
Work has been completed | 100% Completed
Work completed Bill under preparation
Chavasseryparamba WS Sn AE |
Date: 07/09/2023 |
Work has been completed | 100% Completed
Work completed Bill under preparation
Chavasseryparamba WS Sn AE |
Date: 31/08/2023 |
Work has been completed | 100% Completed
Work completed Bill under preparation
Chavasseryparamba WS Sn AE |
Date: 25/08/2023 |
Work has been completed | 100% Completed
Work completed Bill under preparation
Chavasseryparamba WS Sn AE |
Date: 18/08/2023 |
Work in progress | 85% Completed
Pipe Laying work completed. Water connection application submitted is under processing
Chavasseryparamba WS Sn AE |
Date: 10/08/2023 |
Work in progress | 85% Completed
Pipe Laying work completed. Water connection application submitted is under processing
Chavasseryparamba WS Sn AE |
Date: 02/08/2023 |
Work in progress | 85% Completed
Pipe Laying work completed. Water connection application submitted is under processing
Chavasseryparamba WS Sn AE |
Date: 26/07/2023 |
Work in progress | 85% Completed
Pipe Laying work completed. Water connection application submitted is under processing
Chavasseryparamba WS Sn AE |
Date: 18/07/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application.
Chavasseryparamba WS Sn AE |
Date: 11/07/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application.
Chavasseryparamba WS Sn AE |
Date: 06/07/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application.
Chavasseryparamba WS Sn AE |
Date: 30/06/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application.
Chavasseryparamba WS Sn AE |
Date: 25/06/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application.
Kannur PH Dn EE |
Date: 21/06/2023 |
Work in progress | 80% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of Application.
Chavasseryparamba WS Sn AE |
Date: 13/06/2023 |
Work in progress | 70% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of Application.
Chavasseryparamba WS Sn AE |
Date: 09/06/2023 |
Work in progress | 70% Completed
Pipe Laying work completed. Connection work pending due to Non Submission of Application.
Chavasseryparamba WS Sn AE |
Date: 31/05/2023 |
Work in progress | 20% Completed
Work Started, Pipe Supplied