Deposit Work - Pipe line Extension and providing water connection to Staff quarters No.2,No.3 and control room of Pazhassi Irrigation department at Veliyambra near Pazhassi Dam.

Project Deposit Work - Pipe line Extension and providing water connection to Staff quarters No.2,No.3 and control room of Pazhassi Irrigation department at Veliyambra near Pazhassi Dam.
Project Code KNRGOK102214296P1
Type Package
Main Project Deposit Work - Pipe line Extension and providing water connection to Staff quarters No.2,No.3 and control room of Pazhassi Irrigation department at Veliyambra near Pazhassi Dam.
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Deposit Work - Pipe line Extension and providing water connection to Staff quarters No.2,No.3 and control room of Pazhassi Irrigation department at Veliyambra near Pazhassi Dam.
Status On-going
District Kannur
Executing Office Chavasseryparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 100000
TS Number WRD/KWA- CE/NR/EST TS/3376/2023 26 11
Technical specification Pipe line Extension and providing water connection to Staff quarters No.2,No.3 and control room of Pazhassi Irrigation department at Veliyambra near Pazhassi Dam.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/05/2023
Scheduled date of Completion as per agreement 09 Jun 2023
Expected date of Completion 09/06/2023

Processing Dates

TS Date 18 Apr 2023
Estimate Approval 13 Apr 2023
NIT Approval 13 Apr 2023
Tender Closing 27 Apr 2023
Technichal Pre-Qualification 27 Apr 2023
Price bid opening 27 Apr 2023

Approval Dates

Workorder Date 23 May 2023
NA 24 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavasseryparamba WS Sn AE
Date: 16/09/2023

Work has been completed | 100% Completed

Work completed Bill submitted.

Chavasseryparamba WS Sn AE
Date: 12/09/2023

Work has been completed | 100% Completed

Work completed Bill under preparation.