Mattannur WS Sn |
Date: 30/06/2025 |
Work in progress | 28% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain
Mattannur WS Sn |
Date: 18/06/2025 |
Work in progress | 23% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain
Mattannur WS Sn |
Date: 09/06/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 14/05/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 30/04/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 16/04/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 01/04/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 16/03/2025 |
Work in progress | 20% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed)
Mattannur WS Sn |
Date: 07/03/2025 |
Work in progress | 16% Completed
FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed)
Mattannur WS Sn |
Date: 25/02/2025 |
Work in progress | 16% Completed
FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed)
Mattannur WS Sn |
Date: 11/02/2025 |
Work in progress | 16% Completed
FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed)
Mattannur WS Sn |
Date: 28/01/2025 |
Work in progress | 16% Completed
FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed)
Mattannur WS Sn |
Date: 20/01/2025 |
Work in progress | 16% Completed
FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed)
Mattannur WS Sn |
Date: 12/01/2025 |
Work in progress | 15% Completed
FHTC given - 240 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 06/01/2025 |
Work in progress | 14% Completed
FHTC given - 215 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 01/01/2025 |
Work in progress | 14% Completed
FHTC given - 199 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 26/12/2024 |
Work in progress | 14% Completed
FHTC given - 187 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 18/12/2024 |
Work in progress | 13% Completed
work started FHTC given - 135 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 12/12/2024 |
Work in progress | 13% Completed
work started FHTC given - 135 Nos, Pipe laying work in progress.
Mattannur WS Sn |
Date: 03/12/2024 |
Work in progress | 13% Completed
work started FHTC given - 135 Nos, Pipe laying work in progress
Mattannur WS Sn |
Date: 25/11/2024 |
Work in progress | 12% Completed
work started FHTC given - 100 Nos, Pipe laying work in progress
Mattannur WS Sn |
Date: 18/11/2024 |
Work in progress | 12% Completed
work started FHTC given - 100 Nos, Pipe laying work in progress
Mattannur WS Sn |
Date: 11/11/2024 |
Work in progress | 12% Completed
work started FHTC given - 100 Nos
Mattannur WS Sn |
Date: 04/11/2024 |
Work in progress | 11% Completed
work started FHTC given - 100 Nos
Mattannur WS Sn |
Date: 28/10/2024 |
Work in progress | 11% Completed
work started FHTC given - 78 Nos
Mattannur WS Sn |
Date: 21/10/2024 |
Work in progress | 7% Completed
work started FHTC given - 52 Nos
Mattannur WS Sn |
Date: 16/10/2024 |
Work in progress | 2% Completed
work started FHTC given - 45 Nos
Mattannur WS Sn |
Date: 03/10/2024 |
Work in progress | 2% Completed
FHTC given - 23 Nos
Mattannur WS Sn |
Date: 27/09/2024 |
Work in progress | 1% Completed
work started FHTC given - 18 Nos
Mattannur WS Sn |
Date: 05/09/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 28/08/2024 |
Work in progress | 0% Completed
work not started
Mattannur WS Sn |
Date: 21/08/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 06/08/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 31/07/2024 |
Work has started | 0% Completed
work not started