Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Kuttiyattoor Panchayath - Reappropriation -WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs-Pipeline Work |
---|---|
Project Code | KNRJJM102316170P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Kuttiyattoor Panchayath - Reappropriation -WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs-Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Kuttiyattoor Panchayath - Reappropriation -WSS to Kolachery and adjoining panchayaths - Phase III - Balance work - Laying distribution system and providing FHTCs-Pipeline Work |
Status | On-going |
District | Kannur |
Executing Office | Mattannur PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 156600000 |
TS Number | 22845/2023-2024 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/09/2024 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2024 |
Expected date of Completion | 31/12/2024 |
TS Date | 28 Dec 2023 |
---|---|
Estimate Approval | 28 Dec 2023 |
NIT Approval | 17 Jan 2024 |
Tender Closing | 25 Jan 2024 |
Price bid opening | 27 Jan 2024 |
Workorder Date | 16 Feb 2024 |
---|---|
NA | 01 Jun 2024 |
Mattannur WS Sn |
Date: 30/06/2025 |
Work in progress | 28% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain.
Mattannur WS Sn |
Date: 18/06/2025 |
Work in progress | 23% Completed
FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain.