Mattannur WS Sn |
Date: 30/06/2025 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 18/06/2025 |
Work in progress | 0% Completed
work not started
Mattannur WS Sn |
Date: 16/06/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 14/05/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 30/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 16/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 01/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 16/03/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 07/03/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 25/02/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 11/02/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 28/01/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 20/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 12/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 06/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 01/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 26/12/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 18/12/2024 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 12/12/2024 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 03/12/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 25/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 18/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 11/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 04/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 28/10/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
Mattannur WS Sn |
Date: 21/10/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 16/10/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 03/10/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 27/09/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 05/09/2024 |
Work has started | 0% Completed
work not started
Mattannur WS Sn |
Date: 28/08/2024 |
Work has started | 0% Completed
work not started