| Mattannur WS Sn |
| Date: 06/01/2026 |
Work in progress | 42% Completed
Koodali - Thandappuram RHS side BM work completed
| Mattannur WS Sn |
| Date: 29/12/2025 |
Work in progress | 42% Completed
Koodali - Thandappuram RHS side BM work completed
| Mattannur WS Sn |
| Date: 20/12/2025 |
Work in progress | 42% Completed
Koodali - Thandappuram RHS side BM work completed
| Mattannur WS Sn |
| Date: 25/11/2025 |
Work in progress | 40% Completed
40% work completed
| Mattannur WS Sn |
| Date: 14/11/2025 |
Work in progress | 0% Completed
40% work completed.
| Mattannur WS Sn |
| Date: 05/11/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 15/10/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/10/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 22/09/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 19/08/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 31/07/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 21/07/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 30/06/2025 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 18/06/2025 |
Work in progress | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/06/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 14/05/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 30/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 16/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 01/04/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 16/03/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 07/03/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 25/02/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 11/02/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 28/01/2025 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 20/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 12/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 06/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 01/01/2025 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 26/12/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 18/12/2024 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 12/12/2024 |
Work in progress | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 03/12/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 25/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 18/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 11/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 04/11/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 28/10/2024 |
Work has started | 0% Completed
work not started - (Pipe laying work not completed )
| Mattannur WS Sn |
| Date: 21/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 16/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 03/10/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 27/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 05/09/2024 |
Work has started | 0% Completed
work not started
| Mattannur WS Sn |
| Date: 28/08/2024 |
Work has started | 0% Completed
work not started