Project | Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist |
---|---|
Project Code | CLTJJM08206647P1 |
Type | Package |
Main Project | Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing household tap connections(FHTC) by augmentation of existing water supply scheme in Chakkittapara Panchayath. |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 157800000 |
TS Number | 9905/2020-21 |
Technical specification | 1)No of FHTCs-3450nos, 2)Design construction and commissioning of Pump House near WTP 3)Supplying laying testing and commissioning of CWPM from WTP to tankl 1 and Tank2-300mm DI pipe-2100m,250mm DI pipe-2840m and 200mm Di pipe 50m. 4)Construction of GLSR of capacity 250000Ltrs and 150000Ltrs 5) Supplying laying testing and commissioning of distribution system.200mm DI pipe -600m,160mm PVC-3385m, 140mm PVC -3287m,110mm PVC- 8676m and 90mm PVC 98832m. 6)Supplying,erection and commissioning of Pump set |
Contractor | Zubair V (Mob: 9447131582) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/01/2021 |
---|---|
Scheduled date of Completion as per agreement | 21 Jul 2021 |
Expected date of Completion | 31/05/2024 |
TS Date | 22 Oct 2020 |
---|---|
Estimate Approval | 22 Oct 2020 |
Tender Closing | 15 Jan 2021 |
Price bid opening | 19 Jan 2021 |
Workorder Date | 22 Jan 2021 |
---|---|
NA | 03 Feb 2021 |
Kozhikode Project Dn AE4 |
Date: 17/05/2024 |
Work in progress | 98% Completed
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. .
Kozhikode Project Dn AE4 |
Date: 14/05/2024 |
Work in progress | 98% Completed
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. .