Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist

Project Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist
Project Code CLTJJM08206647P1
Type Package
Main Project Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing household tap connections(FHTC) by augmentation of existing water supply scheme in Chakkittapara Panchayath.
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 157800000
TS Number 9905/2020-21
Technical specification 1)No of FHTCs-3450nos, 2)Design construction and commissioning of Pump House near WTP 3)Supplying laying testing and commissioning of CWPM from WTP to tankl 1 and Tank2-300mm DI pipe-2100m,250mm DI pipe-2840m and 200mm Di pipe 50m. 4)Construction of GLSR of capacity 250000Ltrs and 150000Ltrs 5) Supplying laying testing and commissioning of distribution system.200mm DI pipe -600m,160mm PVC-3385m, 140mm PVC -3287m,110mm PVC- 8676m and 90mm PVC 98832m. 6)Supplying,erection and commissioning of Pump set
Contractor Zubair V (Mob: 9447131582)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/01/2021
Scheduled date of Completion as per agreement 21 Jul 2021
Expected date of Completion 31/05/2024

Processing Dates

TS Date 22 Oct 2020
Estimate Approval 22 Oct 2020
Tender Closing 15 Jan 2021
Price bid opening 19 Jan 2021

Approval Dates

Workorder Date 22 Jan 2021
NA 03 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE4
Date: 17/05/2024

Work in progress | 98% Completed

Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. .

Kozhikode Project Dn AE4
Date: 14/05/2024

Work in progress | 98% Completed

Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. .