Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist

Project Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist
Project Code CLTJJM08206647
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing household tap connections(FHTC) by augmentation of existing water supply scheme in Chakkittapara Panchayath.
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 165000000
AS Number ASNO.GO(Rt)No.541/2020
TS Amount (Rs) 157800000
TS Number TS/2020-2021/2020/23756
Total Bill Submitted (Rs) 170986196
Total Bill Paid (Rs) 170986196
Population Benefitted 17250
Capacity in MLD 12.00
Actual Project Completion Date 29 Feb 2024
Coverage Chakkittapara Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Feb 2024 Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. Kozhikode Project Dn AE5
16 Jan 2024 Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress. Kozhikode Project Dn AE5
20 Dec 2023 Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. Ponmalapara concrete reformation work in progress. Kozhikode Project Dn AE4
28 Sep 2023 Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. Neera plant - Thalachira road reformation work in progress. Kozhikode Project Dn AE5
09 Aug 2023 Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1900 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. House connection work in progress. GLSR of capacity 1.5 LL - Plastering Work completed, Valve Chamber work to Urittikarakunne tank work in progress and Road reformation in progress at Vykampara road. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/01/2021
Scheduled date of Completion of the Project 21 Jul 2021
Expected date of Completion 15/04/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 22 Oct 2020

Other details

Project Officers View