Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist
Project |
Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist |
Project Code |
CLTJJM08206647 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing household tap connections(FHTC) by augmentation of existing water supply scheme in Chakkittapara Panchayath. |
Status |
On-going |
District |
Kozhikkode |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
165000000
|
AS Number |
ASNO.GO(Rt)No.541/2020 |
TS Amount (Rs) |
157800000 |
TS Number |
TS/2020-2021/2020/23756 |
Total Bill Submitted (Rs) |
170986196 |
Total Bill Paid (Rs) |
170986196 |
Population Benefitted |
17250 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
29 Feb 2024 |
Coverage |
Chakkittapara Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission:2020-21 phase 1 Chakkittapara Grama Panchayath in Kozhikode Dist |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Feb 2024 |
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress.
|
Kozhikode Project Dn AE5 |
|
16 Jan 2024 |
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. charging work in progress.
|
Kozhikode Project Dn AE5 |
|
20 Dec 2023 |
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. Ponmalapara concrete reformation work in progress.
|
Kozhikode Project Dn AE4 |
|
28 Sep 2023 |
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1940 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. GLSR of capacity 1.5 LL - Plastering Work completed. House connection work in progress. Neera plant - Thalachira road reformation work in progress.
|
Kozhikode Project Dn AE5 |
|
09 Aug 2023 |
Construction of GLSR of capacity 250000Ltrs - Plastering work completed. laying of pumping main in progress. 51 FHTCs and 1900 nos of HTCs including meter fixing are completed at field ,but not geotagged as the distribution system is not charged. Pipe laid ( 1)110 mm PVC - 8408m 2) 140mm PVC-3241m 3)160mm PVC-3500m 4)90 mm PVC-98794m 5)300mm DI -2124m, 6)250mm DI- 2516.5,7)200mm DI- 350 Total = 118933.5 m. House connection work in progress. GLSR of capacity 1.5 LL - Plastering Work completed, Valve Chamber work to Urittikarakunne tank work in progress and Road reformation in progress at Vykampara road.
|
Kozhikode Project Dn AE5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/01/2021 |
Scheduled date of Completion of the Project |
21 Jul 2021 |
Expected date of Completion |
15/04/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
22 Oct 2020 |