Project | State Plan 2019-20 -WSS to Arakuzha & Palakuzha Panchayath |
---|---|
Project Code | EKMGOK0919523 |
Type | Main project |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Laying of pipe line through Arakuzha- Palakuzha road before commencement of tarrng work to BM & BC standard and partial commissioning of the scheme |
Status | Completed |
District | Ernakulam |
Executing Office | Piravam Project Dn |
AS Amount (Rs) | 18680000 |
AS Number | AS No : GO ( Rt) No 893/2016/WRD |
TS Amount (Rs) | 18680000 |
TS Number | 6297/2019-20 |
Total Bill Submitted (Rs) | 14750600 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 28702 |
Capacity in MLD | 5.50 |
Actual Project Completion Date | 11 Nov 2020 |
Coverage | Arakuzha& Palakuzha panchayaths |
Implementation Schedule | Download |
Work Plan | Download |
Date of start of Project | 02/03/2020 |
---|---|
Scheduled date of Completion of the Project | 09 May 2020 |
Expected date of Completion | 13/10/2020 |
AS Date | 07 Sep 2019 |
---|---|
TS Date | 06 Dec 2019 |
Project Officers | View |
---|