Project | State Plan 2019-20 -WSS to Arakuzha & Palakuzha Panchayath |
---|---|
Project Code | EKMGOK0919523P1 |
Type | Package |
Main Project | State Plan 2019-20 -WSS to Arakuzha & Palakuzha Panchayath |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Laying of pipe line through Arakuzha-Palakuzha road before commencement of tarring before tarring to BM&BC standard and partial commisiong of the scheme |
Status | Completed |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 18680000 |
TS Number | 6297/2019-20 |
Technical specification | Laying of pipe line through Arakuzha-Palakuzha road before commencement of tarring before tarring to BM&BC standard and partial commisiong of the scheme |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 02/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 09 May 2020 |
Expected date of Completion | 13/10/2020 |
TS Date | 06 Dec 2019 |
---|---|
Estimate Approval | 06 Dec 2019 |
NIT Approval | 04 Dec 2019 |
Tender Closing | 18 Dec 2019 |
Technichal Pre-Qualification | 21 Dec 2019 |
Price bid opening | 21 Dec 2019 |
Workorder Date | 09 Jan 2020 |
---|---|
NA | 24 Jan 2020 |
Kattappana Project Dn EE |
Date: 14/10/2020 |
Work has been completed | 100% Completed
Work completed.Final bill submitted.