AMRUT 1.0-Kannur Corporation-pipeline extension & providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II
| Project |
AMRUT 1.0-Kannur Corporation-pipeline extension & providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
| Project Code |
KNRAMRUT122315861 |
| Type |
Main project |
| Funding Agency |
AMRUT |
| Category |
AMRUT |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
AMRUT 1.0-Kannur Corporation-pipeline extension & providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Kannur WS Dn |
| AS Amount (Rs) |
243400000
|
| AS Number |
Minutes of the 34th SHPSC of Amrut 1.0 chaired by Chief Secretary, Govt of Kerala on 14-12-23 at 4 p.m |
| TS Amount (Rs) |
29200000 |
| TS Number |
23767/2023-24 |
| Total Bill Submitted (Rs) |
14509416 |
| Total Bill Paid (Rs) |
14509416 |
| Population Benefitted |
5525 |
| Capacity in MLD |
10.00 |
| Actual Project Completion Date |
25 Jan 2025 |
| Coverage |
Puzhathi Zonal |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT 1.0-Kannur Corporation-pipeline extension & amp, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
Kannur WS Sn 3 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 10 Sep 2025 |
work completed, 6.4km pipe laid, 819 FHTC given |
Kannur PH Sn 3 AE |
|
| 30 Aug 2025 |
work completed, 6.4km pipe laid, 819 FHTC given |
Kannur PH Sn 3 AE |
|
| 08 Aug 2025 |
Work has been completed |
Kannur PH Sn 3 AE |
|
| 31 Jul 2025 |
Work has been completed |
Kannur PH Sn 3 AE |
|
| 19 Jul 2025 |
Work has been completed |
Kannur PH Sn 3 AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
18/02/2024 |
| Scheduled date of Completion of the Project |
07 Apr 2024 |
| Expected date of Completion |
15/12/2024 |
Processing Dates
| AS Date |
14 Dec 2023 |
| TS Date |
08 Jan 2024 |