| Project | AMRUT 1.0-Kannur Corporation-pipeline extension & amp, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
|---|---|
| Project Code | KNRAMRUT122315861P1 |
| Type | Package |
| Main Project | AMRUT 1.0-Kannur Corporation-pipeline extension & providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT 1.0-Kannur Corporation-pipeline extension & amp, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone II |
| Status | On-going |
| District | Kannur |
| Executing Office | Kannur WS Sn 3 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 29200000 |
| TS Number | 23767/2023-24 |
| Technical specification | 90mm PVC 8kg/cm2 pipe ,110mm PVC 8kg/cm2 pipe, 160mm PVC 8kg/cm2 pipe |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 18/02/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 08 Apr 2024 |
| Expected date of Completion | 27/03/2024 |
| TS Date | 14 Dec 2023 |
|---|---|
| Estimate Approval | 02 Jan 2024 |
| NIT Approval | 17 Jan 2024 |
| Tender Closing | 23 Jan 2024 |
| Technichal Pre-Qualification | 08 Jan 2024 |
| Price bid opening | 24 Jan 2024 |
| Workorder Date | 31 Jan 2024 |
|---|---|
| NA | 08 Feb 2024 |
| Kannur PH Sn 3 AE |
| Date: 10/09/2025 |
Work has been completed | 100% Completed
work completed, 6.4km pipe laid, 819 FHTC given.
| Kannur PH Sn 3 AE |
| Date: 30/08/2025 |
Work has been completed | 100% Completed
work completed, 6.4km pipe laid, 819 FHTC given.