- Home
- Jal Jeevan Mission (JJM)-Koodali Grama P...
Jal Jeevan Mission (JJM)-Koodali Grama Panchayath - Road reformation work-Koodali Thandappuram Chekkikulam road Ch-Km0/000 to 2/200-Pipeline Work
Project |
Jal Jeevan Mission (JJM)-Koodali Grama Panchayath - Road reformation work-Koodali Thandappuram Chekkikulam road Ch-Km0/000 to 2/200-Pipeline Work |
Project Code |
KNRJJM092116434 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Jal Jeevan Mission (JJM)-Koodali Grama Panchayath - Road reformation work-Koodali Thandappuram Chekkikulam road Ch-Km0/000 to 2/200-Pipeline Work |
Status |
On-going |
District |
Kannur |
Executing Office |
Mattannur PH Sn |
AS Amount (Rs) |
368900000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
8690000 |
TS Number |
9864/2024-2025 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Koodali Grama Panchayath - Road reformation work-Koodali Thandappuram Chekkikulam road Ch-Km0/000 to 2/200-Pipeline Work |
Mattannur PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Jun 2025 |
work not started |
Mattannur WS Sn |
|
18 Jun 2025 |
work not started |
Mattannur WS Sn |
|
16 Jun 2025 |
work not started - (Pipe laying work not completed ) |
Mattannur WS Sn |
|
14 May 2025 |
work not started - (Pipe laying work not completed ) |
Mattannur WS Sn |
|
30 Apr 2025 |
work not started - (Pipe laying work not completed ) |
Mattannur WS Sn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
31 Dec 2024 |
Expected date of Completion |
31/12/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
06 Aug 2024 |