NABARD-Water supply scheme to Mangattidam Zone III in Mangattidam Panchayath of Thalassery tauk in Kannur disrtict

Project NABARD-Water supply scheme to Mangattidam Zone III in Mangattidam Panchayath of Thalassery tauk in Kannur disrtict
Project Code KNRNABARD082111351P1
Type Package
Main Project NABARD-Water supply scheme to Mangattidam Zone III in Mangattidam Panchayath of Thalassery tauk in Kannur disrtict
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Laying distribution network for Kandnakunnu village in Mangattidam panchayath in Thalassery taluk in Kannur District for a total length of 74 km with dia varriying from 250 mm DI K9 pipe to 110 mm PE pipes.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No2
Agreement Number
Agreement Date
TS Amount (Rs) 135400000
TS Number TS/2021-2022/2019/13756
Technical specification Details of distribution 250 mm DI 247 m ,200 mm DI 1552 m, PE pipe 110 mm 46039m ,125 mmPE pipe 2656 m, 100 mm PE pipe 330 m, 90 mm pvc pipe 8 kg/cm2 1300 m ,90 mm pvc 10 kg/cm2 2200 m, 90 mm pvc 12.5 kg 16300 m,110 mm pvc 12.5kg 270 m, 140 mm pvc 8 kg 812 m , 140 mm pvc 12.5 kg 2220 m,

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/07/2022
Scheduled date of Completion as per agreement 28 Oct 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 21 Dec 2021
Estimate Approval 21 Dec 2021
NIT Approval 21 Dec 2021
Tender Closing 04 Apr 2022
Technichal Pre-Qualification 13 Apr 2022
Price bid opening 22 Apr 2022

Approval Dates

Workorder Date 29 Apr 2022
NA 13 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 31/10/2023

Work has been completed | 100% Completed

Work completed and 700 FHTC given 31.07.2023.

Koothuparamba Proj AE 2
Date: 06/10/2023

Work has been completed | 100% Completed

Work completed.