CSME- Deposit work - Providing water supply arrangements to NITCAA Tower , Reccaa Charitable Society and Cochin Reccaa Heights Apartments At Kakkanad- Kollamkudimugal road

Project CSME- Deposit work - Providing water supply arrangements to NITCAA Tower , Reccaa Charitable Society and Cochin Reccaa Heights Apartments At Kakkanad- Kollamkudimugal road
Project Code EKMDEPO10208117
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description CSME- Deposit work - Providing water supply arrangements to NITCAA Tower , Reccaa Charitable Society and Cochin Reccaa Heights Apartments At Kakkanad- Kollamkudimugal road
Status Completed
District Ernakulam
Executing Office Kochi WS Dn
AS Amount (Rs) 254000
AS Number 1000530/2020/4967
TS Amount (Rs) 254000
TS Number TS/2020-2021/2020/4967
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD 0.00
Actual Project Completion Date Date is not specified
Coverage Reccaa Charitable Society and Cochin Reccaa Heights Apartments At Kakkanad- Kollamkudimugal road

Packages

No. Project Name Location View
1 CSME- Deposit work - Providing water supply arrangements to NITCAA Tower , Reccaa Charitable Society and Cochin Reccaa Heights Apartments At Kakkanad- Kollamkudimugal road Trikkakara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Apr 2022 Bill submitted to sub division on 11/04/2022 Thrikkakara Section AE
26 Feb 2022 Work Completed Bill Under Preparation Thrikkakara Section AE
15 Feb 2022 Work completed Kochi WS Dn EE
11 Feb 2022 Pipe laying work completed Thrikkakara Section AE
02 Feb 2022 Work delayed due to the delay in supply of pipes. which was not fixed the latest rate Thrikkakara Section AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/12/2020
Scheduled date of Completion of the Project 16 Jan 2021
Expected date of Completion 28/02/2022

Processing Dates

AS Date 07 Sep 2020
TS Date 12 Oct 2020

Other details

Project Officers View