Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Apr 2022 | Bill submitted to sub division on 11/04/2022 | Thrikkakara Section AE | |
26 Feb 2022 | Work Completed Bill Under Preparation | Thrikkakara Section AE | |
15 Feb 2022 | Work completed | Kochi WS Dn EE | |
11 Feb 2022 | Pipe laying work completed | Thrikkakara Section AE | |
02 Feb 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE | |
29 Jan 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE | |
28 Jan 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE | |
27 Jan 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE | |
25 Jan 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE | |
20 Jan 2022 | Work delayed due to the delay in supply of pipes. which was not fixed the latest rate | Thrikkakara Section AE |