Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Project Code
KLMDEPO03217949
Type
Main project
Funding Agency
DEPO
Category
Deposit Work
Type of scheme
Water Supply
Scheme
DEPO
Description
Deposit work by Perinadu Grama Panchayath as per project No.269/21 for commissioning a tube well drilled by GWD at Chirakkonam in ward.8.Work consists of construction of pumphouse,supply and erection of sub.pumpset,laying 110mm PVC pipe(350m),interconnection work etc
Status
Completed
District
Kollam
Executing Office
Kollam PH Sn
AS Amount (Rs)
1250000
AS Number
U000000851855422
TS Amount (Rs)
1250000
TS Number
2115/2021-2022
Total Bill Submitted (Rs)
0
Total Bill Paid (Rs)
0
Population Benefitted
600
Capacity in MLD
1.50
Actual Project Completion Date
Date is not specified
Coverage
Perinadu
Packages
No.
Project Name
Location
View
1
Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Kollam PH Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
16 Nov 2021
The Work was completed
Kollam PH Sn AE
08 Nov 2021
95% completed and started for electric supply and pump erection.
Kollam PH Dn EE
29 Oct 2021
KSEB Power supply work was not completed. The Demand notice amount of Amount Rs 1,09,374.00 paid to KSEB,Kundara office for the electric work and wait for Supply.
Kollam PH Sn AE
16 Oct 2021
Work in progress - 90% Completed
All civil works was completed wait for electric supply and pump erection.