Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath

Project Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Project Code KLMDEPO03217949P2
Type Package
Main Project Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work-PerinaduGramaPanchayath-Annual Plan 2020-21-Project No.269/21-Commissioning of tube well at Chirakkonam - Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath
Status On-going
District Kollam
Executing Office Kollam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1250000
TS Number TS/2021-2022//2020/26208
Technical specification Construction of new pump house ,Supply and erection of pump set,Pipe laying and interconnection work etc. in Nattuvathukkal area in PerinaduPanchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/08/2021
Scheduled date of Completion as per agreement 31 Oct 2021
Expected date of Completion 31/10/2021

Processing Dates

TS Date 18 May 2021
Estimate Approval 18 May 2021
NIT Approval 20 May 2021
Tender Closing 29 May 2021
Technichal Pre-Qualification 02 Jun 2021
Price bid opening 02 Jun 2021

Approval Dates

Workorder Date 21 Jun 2021
NA 02 Aug 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam PH Sn AE
Date: 22/11/2021

Work has been completed | 100% Completed

Work was completed ,Trial run,.

Attached images

img

Kollam PH Dn EE
Date: 08/11/2021

Work in progress | 95% Completed

Work in progress All civil works was completed and started for electric supply and pump erection..