| Project | "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III |
|---|---|
| Project Code | KLMGOK1217493P1 |
| Type | Package |
| Main Project | "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 40500000 |
| TS Number | TS/2018-2019/2018/18 |
| Technical specification | 3.4 LL SUMP and allied works with distribution in zone III |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/03/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 30 May 2021 |
| Expected date of Completion | 31/07/2021 |
| TS Date | 15 Oct 2018 |
|---|---|
| Estimate Approval | 15 Oct 2018 |
| NIT Approval | 15 Nov 2018 |
| Tender Closing | 22 Dec 2018 |
| Technichal Pre-Qualification | 24 Dec 2018 |
| Price bid opening | 26 Dec 2018 |
| Workorder Date | 07 Feb 2019 |
|---|---|
| NA | 01 Mar 2019 |
| Kollam Project HD |
| Date: 24/08/2021 |
Work has been completed | 100% Completed
work completed on 31.7.21.
| Kollam Project HD |
| Date: 23/08/2021 |
Work in progress | 99% Completed
Trial running works in progress.