"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III

Project "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III
Project Code KLMGOK1217493P1
Type Package
Main Project "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 40500000
TS Number TS/2018-2019/2018/18
Technical specification 3.4 LL SUMP and allied works with distribution in zone III

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/03/2019
Scheduled date of Completion as per agreement 30 May 2021
Expected date of Completion 31/07/2021

Processing Dates

TS Date 15 Oct 2018
Estimate Approval 15 Oct 2018
NIT Approval 15 Nov 2018
Tender Closing 22 Dec 2018
Technichal Pre-Qualification 24 Dec 2018
Price bid opening 26 Dec 2018

Approval Dates

Workorder Date 07 Feb 2019
NA 01 Mar 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 24/08/2021

Work has been completed | 100% Completed

work completed on 31.7.21.

Kollam Project HD
Date: 23/08/2021

Work in progress | 99% Completed

Trial running works in progress.