"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "
Project |
"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " |
Project Code |
KLMGOK1217493 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "- construction of 3.4 LL sump & pump House proposed at vayala School Compound and distribution of zone III
|
Status |
Completed |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
41000000
|
AS Number |
GO (Rt)No.1040/2017/WRD |
TS Amount (Rs) |
40500000 |
TS Number |
TS/2018-2019/2018/18 |
Total Bill Submitted (Rs) |
23423254 |
Total Bill Paid (Rs) |
4927784 |
Population Benefitted |
12000 |
Capacity in MLD |
1.20 |
Actual Project Completion Date |
31 Jul 2021 |
Coverage |
Punaloor constituency Part 145479 total Population of the scheme 12000 from this sum |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Aug 2021 |
trail running works pending. |
Kollam Project HD |
|
27 Jul 2021 |
Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress |
Kollam Project HD |
|
24 Jul 2021 |
Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress |
Kollam Project HD |
|
22 Jul 2021 |
Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress |
Kollam Project HD |
|
21 Jul 2021 |
Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress |
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/03/2019 |
Scheduled date of Completion of the Project |
31 Jul 2021 |
Expected date of Completion |
31/07/2021 |
Processing Dates
AS Date |
20 Dec 2017 |
TS Date |
15 Oct 2018 |