"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "

Project "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "
Project Code KLMGOK1217493
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised "- construction of 3.4 LL sump & pump House proposed at vayala School Compound and distribution of zone III
Status Completed
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 41000000
AS Number GO (Rt)No.1040/2017/WRD
TS Amount (Rs) 40500000
TS Number TS/2018-2019/2018/18
Total Bill Submitted (Rs) 23423254
Total Bill Paid (Rs) 4927784
Population Benefitted 12000
Capacity in MLD 1.20
Actual Project Completion Date 31 Jul 2021
Coverage Punaloor constituency Part 145479 total Population of the scheme 12000 from this sum
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " -Construction of 3.4 LL sump cum pump house and distribution system zone III Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Aug 2021 trail running works pending. Kollam Project HD
27 Jul 2021 Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress Kollam Project HD
24 Jul 2021 Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress Kollam Project HD
22 Jul 2021 Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress Kollam Project HD
21 Jul 2021 Works for ...3.14 LL sump completed....pumphouse finishing works and hand rail fixing works in progress....for distribution ... interconnection works in progress Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2019
Scheduled date of Completion of the Project 31 Jul 2021
Expected date of Completion 31/07/2021

Processing Dates

AS Date 20 Dec 2017
TS Date 15 Oct 2018

Other details