| Project | State plan- Optimization - Completion of WSS to Manimala and adjoining 4 panchayats |
|---|---|
| Project Code | KTMGOK1217594 |
| Type | Main project |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | STATE PLAN-2017-18-OPTIMIZATION OF PRODUCTION AND TRANSMISSION- Completion of WSS to Manimala and adjoining 4 panchayats benefitting population of 85746 in the entire scheme area |
| Status | Completed |
| District | Kottayam |
| Executing Office | Kottayam Project Dn |
| AS Amount (Rs) | 18300000 |
| AS Number | 1040/2017/WRD |
| TS Amount (Rs) | |
| TS Number | |
| Total Bill Submitted (Rs) | 11774601 |
| Total Bill Paid (Rs) | 4147000 |
| Population Benefitted | 85746 |
| Capacity in MLD | 9.00 |
| Actual Project Completion Date | 05 Jan 2020 |
| Coverage | Vellavoor, Manimal, Cheruvally, Vazhoor, Anicad villages |
| No. | Project Name | Location | View |
|---|---|---|---|
| 1 | Clear Water Pump sets at WTP for Karuthamanjadi,Ullayam,Challoli,Poovatholi tanks | Kottayam Project Dn | |
| 2 | Gap filling, Interconnections required for the recommissioning of the scheme and commissioning of distribution system in Phase 1 Zone 3 and Phase 2-Zone 1 | Kottayam Project Dn | |
| 3 | Laying scour pipeline from 9 MLD WTP at Manimala and maintenance works at WTP and RWPH. | Kottayam Project Dn |
| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Jun 2021 | work completed , bill prepared and submitted | Kottayam Project Dn AE1 | |
| 19 Apr 2021 | work completed , Package 3 final preparing | Kottayam Project Dn AE1 | |
| 17 Mar 2021 | out of three packages one package is to be finished. The transformer complaint is the restriction in completing the work. Expect to resume balance work from this week onwards | Kottayam Project Dn AE1 | |
| 15 Mar 2021 | transformer repair in progress for restarting pumping and charging the pipe line | Kottayam Project Dn AE1 | |
| 07 Mar 2021 | Package 3 has to be finished , for that kSTP WORK NEED TO BE FINISHED | Kottayam Project Dn AE1 |
| Review Date | Review Message | Review Attended By |
|---|---|---|
| 11 Feb 2021 | MORE PHOTOS TO BE ADDED | AE |
| 03 Feb 2021 | Add present status of KSTP work with photographs | AEE,AE |
| Date of start of Project | 05/12/2018 |
|---|---|
| Scheduled date of Completion of the Project | Date is not specified |
| Expected date of Completion | 28/02/2021 |
| AS Date | 20 Dec 2017 |
|---|
| Project Officers | View |
|---|