Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State plan- Optimization - Completion of WSS to Manimala and adjoining 4 panchayats

Project State plan- Optimization - Completion of WSS to Manimala and adjoining 4 panchayats
Project Code KTMGOK1217594
Type Main project
Category State plan
Description STATE PLAN-2017-18-OPTIMIZATION OF PRODUCTION AND TRANSMISSION- Completion of WSS to Manimala and adjoining 4 panchayats benefitting population of 85746 in the entire scheme area
District Kottayam
Execution Kottayam Project Dn
AS Amount (Rs) 18300000.00
Total Bill Submitted (Rs) 9515000.00
Total Bill Paid (Rs) 4147000.00
Coverage Vellavoor, Manimal, Cheruvally, Vazhoor, Anicad villages

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Apr 2021 work completed , Package 3 final preparing Kottayam Project Dn AE1
17 Mar 2021 out of three packages one package is to be finished. The transformer complaint is the restriction in completing the work. Expect to resume balance work from this week onwards Kottayam Project Dn AE1
15 Mar 2021 transformer repair in progress for restarting pumping and charging the pipe line Kottayam Project Dn AE1
07 Mar 2021 Package 3 has to be finished , for that kSTP WORK NEED TO BE FINISHED Kottayam Project Dn AE1
22 Feb 2021 The whole work can be completed after re erecting transformer after repair Kottayam Project Dn AE1

Project Review

See All Review messages
Review Date Review Message Review Attended By
11 Feb 2021 MORE PHOTOS TO BE ADDED AE
03 Feb 2021 Add present status of KSTP work with photographs AEE,AE

Packages

No. Project Name Location View
1 Clear Water Pump sets at WTP for Karuthamanjadi,Ullayam,Challoli,Poovatholi tanks Kottayam Project Dn
2 Gap filling, Interconnections required for the recommissioning of the scheme and commissioning of distribution system in Phase 1 Zone 3 and Phase 2-Zone 1 Kottayam Project Dn
3 Laying scour pipeline from 9 MLD WTP at Manimala and maintenance works at WTP and RWPH. Kottayam Project Dn

Duration & Sanction dates

Date of Sanction 20/12/2017
Date of start 05/12/2018
Expected date of Completion 28/02/2021

Other details

Project Officers View
Funding Agency GOK

Processing Dates

AS Date 20 Dec 2017

Location