| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Jun 2021 | work completed , bill prepared and submitted | Kottayam Project Dn AE1 | |
| 19 Apr 2021 | work completed , Package 3 final preparing | Kottayam Project Dn AE1 | |
| 17 Mar 2021 | out of three packages one package is to be finished. The transformer complaint is the restriction in completing the work. Expect to resume balance work from this week onwards | Kottayam Project Dn AE1 | |
| 15 Mar 2021 | transformer repair in progress for restarting pumping and charging the pipe line | Kottayam Project Dn AE1 | |
| 07 Mar 2021 | Package 3 has to be finished , for that kSTP WORK NEED TO BE FINISHED | Kottayam Project Dn AE1 | |
| 22 Feb 2021 | The whole work can be completed after re erecting transformer after repair | Kottayam Project Dn AE1 | |
| 17 Feb 2021 | pipelaying pending | Kottayam Project Dn AE1 | |
| 15 Feb 2021 | KSTP road work in progress . Pipelaying works are still pending | Kottayam Project Dn AE1 | |
| 15 Feb 2021 | Pipe laying work in KSTP road work in progress | Kottayam Project Dn AE1 | |
| 11 Feb 2021 | KSTP side cutting for widening is in progress . Once the same completed they will lay the pipelines. Pipes arrived after testing . | Kottayam Project Dn AE1 |