NABARD-RIDF-XXIV-WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II

Project NABARD-RIDF-XXIV-WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II
Project Code PTANABARD1219604
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description This scheme includes Construction of intermediate storage tanks, Laying CWPM, RWPM,distribution lines, construction of transformer building, supply and erection of transformer, pumpsets etc.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 1200000000
AS Number 107/2019/WRD
TS Amount (Rs) 754500000
TS Number TS/2019-20/2018/13798
Total Bill Submitted (Rs) 495626666
Total Bill Paid (Rs) 326584373
Population Benefitted 146396
Capacity in MLD 13.00
Actual Project Completion Date 30 May 2024
Coverage Seethathode and Perunad panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 NABARD RIDF XXIV - WSS to Seethathode & Nilakkal Plappally area in Perunad pt. of Pathanamthitta Dist. Phase II-Package I - Balance works Adoor Project Dn
2 WSS to Seethathode & Perunadu Panchayats (Nilackal)-PhaseII-Package 1 Adoor Project Dn
3 WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II- Package II Adoor Project Dn
4 WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II- Package III Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Aug 2022 Package I Estimate for balance work Tendered Adoor Project Dn AE 4
01 Jul 2022 Package 1 - Work terminated by SE. Adoor Project Dn EE
29 May 2022 Package 1 ongoing, Package 2 estimate submitted for tendering, Package 3 - Soil investigation for OH tank completed. Design started. Adoor Project Dn EE
16 Mar 2022 Package 1 ongoing Package 2 tendered Package 3 - Estimate submitted for TS. Adoor Project Dn EE
02 Mar 2022 Plappally - Angamoozhy restoration nearing completion. Raw water pumping main ongoing. Gap connection and testing of pipelines in Nilakkal started Adoor Project Dn EE

Project Review

See All Review messages
Review Date Review Message Review Attended By
21 May 2022 Review by Honble MLA Konni. Sri Janish Kumar. Honble MLA demanded that considering the inordinate delay of completion of work, the contractor shall be terminated. Directed CLO KWA over phone to issue the legal opinion on termination without delay. Plappally Angamoozhy stretch should be restored without delay. Honble MLA Konni Sri Janish Kumar, EE KWA, AEE PWD Ranni.
18 May 2022 Statement of project delay upto 15/05/2022 based on revised approved schedule issued to contractor. Honble High court has taken a suo moto case due to delay in this work. Legal Opinion for termination of work is pending from CLO KWA based on SEs letter dated 25/02/2022. EE

Duration & Sanction dates

Date of start of Project 22/11/2019
Scheduled date of Completion of the Project 17 Nov 2023
Expected date of Completion 17/11/2023

Processing Dates

AS Date 21 Feb 2019
TS Date 27 Jun 2019

Other details

Project Officers View