DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work

Project DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work
Project Code EKMDEPO122315787P1
Type Package
Main Project DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work
Status On-going
District Ernakulam
Executing Office Vytilla Section 1
Agreement Number
Agreement Date
TS Amount (Rs) 850000
TS Number WRD/KWA-CE(CR)/EST_TS/25325/2023_26_1_1
Technical specification DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work
Contractor Biju T.R (Mob: 9349415119)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/03/2024
Scheduled date of Completion as per agreement 31 May 2024
Expected date of Completion 31/05/2024

Processing Dates

TS Date 02 Feb 2024
Estimate Approval 31 Jan 2024
NIT Approval 09 Feb 2024
Tender Closing 13 Feb 2024
Technichal Pre-Qualification 13 Feb 2024
Price bid opening 15 Feb 2024

Approval Dates

Workorder Date 19 Feb 2024
NA 22 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla Section AE - 1
Date: 05/04/2024

Work has been completed | 100% Completed

E bill submitted.

Vytilla Section AE - 1
Date: 04/04/2024

Work has been completed | 100% Completed

Reconcreting completed.